File PR-2508 · Commercial

Sandton Deck Structure

Structural deck package on a high-rise commercial build with two tower cranes in service.

Levels
12 / 19
Deck cycle
7 days
Crane hrs
2 180
Incidents
0

The brief

A multi-level commercial structure with a tight crane envelope and a live public edge on two boundaries. Programme certainty mattered more than unit rate.

How it was built

  1. 01Deck cycle fixed at seven working days and published to every subcontractor at mobilisation.
  2. 02Edge protection and public-interface controls designed before the first lift.
  3. 03Electrical first-fix built into the deck cycle rather than chased afterwards.
  4. 04Weekly progress photography and a dated register issued to the client team.

Outcome

Deck cycle has held for eleven consecutive floors. Currently at level 12 of 19 with the finishing package mobilising behind the structure.

Evidence

Site frames

Timber and steel roof truss framing set out over a structure
Temporary framing to the roof plant deck
Interior window and finishing work in progress on a building
Glazing and finishing, level 04
Johannesburg skyline seen across the surrounding suburbs
Context — the northern skyline from the deck