File PR-2377 · Exterior works

Glen Marais Driveway & Kerbing

Cobblestone driveway, kerbing and stormwater falls on a sloped residential approach.

Area
310 m²
Base
150 mm G5
Fall
1 : 60
Snags
2 closed

The brief

An existing driveway had failed twice on a thin base and was ponding water against the garage threshold. The client wanted the surface rebuilt properly rather than patched a third time.

How it was built

  1. 01Failed surface lifted and the sub-base tested before any new material was ordered.
  2. 02Levels reset to move water away from the threshold and into a new channel.
  3. 03Setting-out lines pegged and approved with the client before laying started.
  4. 04Edge restraint and kerbing cast first so the field could be laid tight to a fixed line.

Outcome

Handed over in three weeks with no ponding after the first summer storm season. Two subsequent referrals in the same street.

Evidence

Site frames

Roadworks crew laying kerbing along a new carriageway edge
Kerbing and edge restraint set to line
Close detail of interlocking paving blocks being laid to pattern
Block laying, herringbone field
Close detail of masonry setts laid against a face-brick wall
Sett detail against the boundary
More templates