File PR-2290 · Residential

Midrand Estate Earthworks

Bulk earthworks, terracing and platform preparation across eighteen residential erven.

Erven
18 no.
Cut / fill
21 400 m³
Export
0 m³
Layer tests
96 passed

The brief

Eighteen sloping erven had to be cut and filled to buildable platforms without exporting material off site, and without holding up the first four house contracts.

How it was built

  1. 01Cut-to-fill balance modelled so no material left the site.
  2. 02Platforms released in batches of four so house builders could start behind us.
  3. 03Compaction tested per layer and recorded against each erf number.
  4. 04Temporary stormwater cut in before the first rain to protect the open faces.

Outcome

All eighteen platforms released inside nine weeks with layer-works records issued per erf. No material imported or exported.

Evidence

Site frames

Project team reviewing programme and drawings around a table
Platform release sequence, weekly review
Site walk-through inspection with the client and site manager
Layer-works inspection with the client team
Building facade painted with the South African flag