Isando Piling & Platform
Piled foundations and a load-bearing platform for a distribution facility on poor ground.
- Piles
- 112 no.
- Platform
- 3 400 m²
- Concrete
- 740 m³
- Lost days
- 0
The brief
The site had variable fill to a depth of roughly four metres and could not carry a conventional strip foundation. The client needed a platform that would take heavy vehicle loading without long-term settlement.
How it was built
- 01Geotechnical review and piling layout agreed before any plant moved onto site.
- 02Rig mobilised with a fixed daily production target and a survey check on every pile position.
- 03Pile caps and ground beams cast in sequence so the surface bed could follow without a stand-down.
- 04Surface bed poured in bays with jointing set out to the client’s vehicle circulation plan.
Outcome
Platform handed over inside the fourteen-week programme with a full set of pile records, survey positions and concrete test results.